On a winter morning, dog-walkers and joggers still loop the fig-tree paths of Victoria Park, a stretch of inner-Brisbane green space a few minutes from the CBD that many locals also know by its older name, Barrambin. Sports fans a few kilometres away still file into the Gabba, the ground that was meant to be rebuilt for 2032 and now will not be. Within a decade, a large slice of the park will instead sit inside the footprint of a 63,000-seat Olympic stadium. How the Games' main venue ended up here — after four years, three premiers and two abandoned plans for a different site altogether — says less about sport than about how Queensland makes, unmakes and remakes an expensive decision in public.
From the Gabba to Barrambin
Brisbane won the right to host the 2032 Olympic and Paralympic Games in 2021, on a bid built around an unusually long eleven-year run-up to the Games — well beyond the seven years typical of past hosts — so that venue-building could double as ordinary state infrastructure rather than one-off Olympic extras. A joint South East Queensland feasibility study had scoped the bid as early as February 2019, working on the assumption that Brisbane's existing stadiums, including the Gabba, could largely be reused rather than replaced. The Palaszczuk Labor government's first firm answer for a main stadium was, instead, to rebuild the Gabba, Brisbane's century-old cricket and AFL ground, at a cost then put at about $1 billion (2021, approx.). By February 2023 that estimate had risen to about $2.7 billion (approx.) — nearly triple — with the government pointing to pandemic-era construction inflation and global supply pressures.
Facing a stadium whose price had almost tripled before a shovel had turned, the government commissioned an independent Sport Venue Review, led by former Brisbane Lord Mayor Graham Quirk. The panel ran a 60-day process, drew more than 900 public submissions, held around 130 stakeholder meetings and made 28 site visits. It reported to the Minister for State Development on 15 March 2024, recommending the Gabba rebuild be dropped in favour of a new 55,000-seat stadium at Victoria Park, priced at about $3.4 billion (approx.), alongside a roughly $1.6 billion (approx.) upgrade of the Queensland Sport and Athletics Centre at Nathan for athletics and aquatics, with Suncorp Stadium used for the opening and closing ceremonies.
Premier Steven Miles, who had replaced Annastacia Palaszczuk in December 2023, rejected his own review's central recommendation within days, arguing the state could not justify a new stadium costing billions while Queenslanders faced cost-of-living pressure. Labor went into the October 2024 state election without a settled new-stadium plan — and lost office to the LNP under David Crisafulli, who had spent the campaign attacking Labor's indecision and promising that no new stadium would be built.
The 100-day review and the reversal
The incoming government inherited Games machinery that was itself mid-restructure. In July 2024 the outgoing Labor government had replaced two earlier offices with a single statutory authority to manage venues; in November 2024 the new Crisafulli government renamed it the Games Independent Infrastructure and Coordination Authority (GIICA) — the body now responsible for delivering 17 new and upgraded venues within a $7.1 billion combined state and federal funding envelope. Crisafulli also ordered a fresh 100-day review of venue options, this time testing four rival stadium concepts for the main venue: a Victoria Park stadium and aquatic centre (about $5.4 billion, approx.); a rebuilt Gabba; a "Gabba West" option built above Woolloongabba railway station; and a Mayne Yard stadium modelled on Perth's, near the CBD (about $6 billion, approx.).
The review reported on 8 March 2025. On 25 March 2025, Crisafulli announced the 2032 Delivery Plan: a new 63,000-seat Brisbane Stadium would be built at Victoria Park after all, at a cost then stated at about $3.8 billion (approx.), inside the same $7.1 billion venues envelope (the Australian Government's contribution capped at about $3.4 billion, approx.). The Premier acknowledged he was reversing his own election commitment, arguing the Gabba was ageing and no longer fit to carry the Games, and that a stadium later used permanently by the Brisbane Lions, Queensland Bulls and Brisbane Heat was the more durable legacy. The review found roughly two-thirds of the park would remain public green space.
The strongest case
An eleven-year build was designed to leave more than a stadium behind
Brisbane's bid deliberately built in a long lead time so Games venues could serve as everyday state infrastructure rather than stranded Olympic assets, and on that logic the Gabba genuinely was ageing and due for major work regardless of the Games. A permanent 63,000-seat stadium that becomes the long-term home of the Lions, the Bulls and the Heat is arguably a more useful legacy than propping up an ageing ground for one event. GIICA's mandate covers 17 venues spread across the state, not just Brisbane, and the government's own review found most of Victoria Park would stay public parkland. Large infrastructure programs rarely move in a straight line, and testing rival options twice before locking in a multibillion-dollar commitment is, on its face, more careful than simply pressing ahead with the original Gabba plan once its cost had nearly tripled.
What the numbers show
The clearest independent account of how this has been managed comes from the Queensland Audit Office (QAO), which tabled Preparing for the Brisbane Games on 13 December 2024, the first in a planned series of audits covering the Games. Its central finding was that the responsible entities had not built a consolidated budget capturing all estimated costs to deliver the Games — meaning no single Queensland Government document adds venues, operations, transport and athlete-village costs into one confirmed total. Separate published figures the audit could point to included $435 million (approx.) in operational coordination costs and $155 million (approx.) for early athlete-village enabling works, on top of the $7.1 billion venues program — three more line items that, on the QAO's own finding, nobody had yet added into one total. The same audit found whole-of-Games risk management, across roughly ten major work programs, was still being developed, and that the legacy strategy, Elevate 2042, set four broad themes without specific targets or a named owner to track them after 2032.
A further data point complicates the picture. When Games organisers unveiled the stadium's "Queenslander"-inspired design in January 2026, media reporting cited a construction cost of about $2.3 billion (approx.) — lower than the $3.8 billion figure attached to the same stadium ten months earlier. Whether that reflects a genuine saving, a narrower scope such as construction only, excluding precinct and enabling works, or simply the absence of one settled number, is not something public documents currently resolve. That gap is exactly what the Auditor-General flagged in December 2024.
The whiplash has a price
Every reversal in this saga carries a cost even when it lands on a better final answer. Design and planning work sunk into the Gabba rebuild between 2021 and 2024, and into the rejected Victoria Park option from the Quirk review before Crisafulli's own version overtook it a year later, does not appear as a line item in any public document, because, as the Auditor-General found, no consolidated ledger exists to show it. Four separate cost or site positions in four years — Gabba, a bigger Gabba, a rejected Victoria Park, an adopted Victoria Park — is not the record of a government testing options once and moving on; it is the record of a decision that took three premiers and two governments to settle, each one governing or campaigning against the plan the last one held.
The most direct cost is trust. Crisafulli won the 2024 election partly by ruling out a new stadium and criticising Labor's own indecision on the same question. Five months into government, his own review recommended the option he had campaigned against, and he adopted it in full. That reversal is not disqualifying by itself — governments are entitled to change position on new evidence — but a review commissioned and controlled by the same government that announces its outcome, run to a 100-day deadline, does not carry the weight of a genuinely arm's-length process, and the political convenience of landing on the answer the Quirk review had already floated a year earlier is hard to ignore.
The site itself carries a cost the budget papers do not capture. Victoria Park, or Barrambin, has cultural significance to the Turrbal people as a traditional gathering and camping ground, and multiple applications have been lodged with the Commonwealth Environment Minister under national cultural heritage protection law seeking to alter or block construction. The community group Save Victoria Park also published its own cost-risk analysis on 7 October 2025, arguing the stadium's cost per seat is more than double that of the North Queensland Stadium in Townsville and that the build risks running six months late; a spokesperson for Deputy Premier Jarrod Bleijie disputed the delay claim, saying the government's own project assessment work showed the stadium could still be delivered on time and on budget. Neither side's claim has yet been tested against a completed build, but the dispute shows how much remains unresolved only six years from the scheduled opening ceremony. Two of the heritage applications lodged with the Commonwealth have already been withdrawn or rejected on narrow grounds, while others remain live, and an independent facilitator has since been appointed to mediate between cultural-site protection and the construction schedule — itself a sign that the site question the 100-day review was meant to close is not fully closed.
No single Queensland Government document says what the Brisbane Games will cost — that is not a critic's claim, it is the state's own Auditor-General's finding, tabled in December 2024.
The risk to the future
A compressed build, an unresolved heritage dispute and no confirmed final cost
Early works on the Brisbane Stadium were announced in March 2026, with a delivery partner, a Laing O'Rourke–AECOM joint venture appointed in December 2025, only recently on board. That leaves roughly six years to deliver a 63,000-seat stadium ahead of the Games' scheduled opening on 23 July 2032, on a site where First Nations heritage applications to the Commonwealth remain unresolved and where the last two headline cost figures, from March 2025 and January 2026, do not obviously reconcile. If costs rise again, as they did twice between 2021 and 2025, Queensland's room to move will be far narrower than it was in 2023 or 2025: the Games date is fixed, the site is now largely locked in, and a fourth reversal this close to 2032 would cost more than the three that came before it. The Auditor-General's own recommendation, a single consolidated whole-of-Games budget, has not yet been shown to exist. Until it does, Queenslanders are being asked to trust a total cost that nobody in government has actually published.