Northern Rivers flood recovery and Lismore

In plain terms

The floods that hit Lismore and the Northern Rivers wrecked whole streets. The buyback scheme that followed is the biggest of its kind ever tried in Australia.

Four years on, the scheme meant to give people somewhere to move to has delivered nothing. Not one new home. Not one block of land.

So people sit next to empty blocks, or in repaired homes nobody will buy. Many cannot afford insurance any more. Some have simply given up waiting. Labor owns the finish line now, and there is still no clear date for it.

The 90-second read

Years on from catastrophic floods, buybacks and rebuilding remain unfinished for a traumatised community.

The Resilient Homes Program is the largest voluntary flood buyback ever attempted in Australia, and how it finishes will decide whether the Northern Rivers becomes a smaller, safer region or a stalled one — dotted with empty buyback blocks, unsellable repaired homes and residents who simply gave up waiting. Four years on, the companion Resilient Lands Program has not delivered a single new home or block of land for people to move to, and insurance is now unaffordable for many of the households trying to stay. The decisions made in the next two years will determine whether Lismore remains a functioning regional centre or drifts into a slow-motion retreat with no clear finish line.

In South Lismore, on streets where older timber houses sit high on their original stumps and newer infill sits low on concrete slabs, it is still possible in 2026 to find a for-sale sign nailed to an empty block — the house removed after a state buyback, the land now waiting to become something else. On the same street it is just as possible to find a family still living behind a freshly repaired front door, waiting for a buyback offer that has not come, and a household two doors down asking why their raised and retrofitted home now carries an insurance quote bigger than their mortgage repayment. All three households lived through the same flood, on the same night in late February 2022, when the Wilsons River peaked at 14.4 metres in Lismore — 2.3 metres above any level ever recorded — and again five weeks later, on 30 March, before the town had finished drying out (NSW Audit Office, Flood housing response, 22-Feb-2024). Four years on, their experiences of "recovery" look nothing alike, and that gap is the story of this program.

Thirteen people died in the Northern Rivers floods of February–March 2022. Across the region, 4,055 properties were left uninhabitable and a further 10,849 were damaged — a disaster on a scale no Australian state had previously tried to recover from through a large, voluntary home buyback (NSW Audit Office, 22-Feb-2024). What New South Wales built in response, and how well it has been run since, is the subject of what follows.

What the government did

The independent NSW Flood Inquiry, led by former NSW Chief Scientist Mary O'Kane and former Police Commissioner Mick Fuller, reported in August 2022 after receiving 1,494 submissions and holding 144 meetings across the affected regions, including in Lismore itself. Among its central recommendations was that government use its planning and funding powers to move the highest-risk households off the floodplain rather than simply rebuild them in place (NSW Flood Inquiry, Aug-2022). The then-Coalition government, in its final months in office, answered with the Resilient Homes Program, which opened for applications in November 2022 — four months before the March 2023 election that brought Chris Minns' Labor government to power. Almost the entire delivery life of the program has therefore run under Labor, even though its design and initial funding envelope were set by the government it replaced.

The Resilient Homes Program, jointly funded by the NSW and Commonwealth governments, offers eligible Northern Rivers homeowners one of three paths: a voluntary buyback of the property at its pre-flood value, a grant of up to $100,000 toward raising the house above flood level or rebuilding, or up to $50,000 toward a flood-resilient retrofit (NSW Reconstruction Authority, Resilient Homes Program fact sheets, 2024–2026). A further $40 million extends parts of the program to flood-hit Central West communities such as Eugowra and Forbes, on top of the figures below. The Northern Rivers-focused Resilient Homes Program ($880 million) and its companion Resilient Lands Program ($100 million) — meant to prepare flood-free land so bought-back households have somewhere nearby to move to — together represent a combined $980 million commitment (NSW Audit Office, The Resilient Homes and Resilient Lands Programs, 20-May-2026).

None of it is compulsory: households can accept an offer or decline it, and thousands took time to decide either way, which is one reason the program's own targets have shifted. In August 2025 the Reconstruction Authority reset its delivery targets, from an original 1,345 buybacks down to a revised 1,000 buybacks plus 600 home raises or retrofits, citing community feedback (NSW Audit Office, 20-May-2026). Settlement deadlines have also moved: buyback purchases are now due to be settled by 30 June 2026, relocations by the end of 2026, and resilient works completed by 31 March 2027, with the program winding up by mid-2027 (NSW Reconstruction Authority, Resilient Homes Program, 2026).

The strongest case

No Australian government has attempted a buyback at this scale, on a voluntary basis

Put the difficulty of this task at its highest, because it is real. The revised target of 1,000 buybacks plus 600 resilient retrofits is, by an order of magnitude, the largest voluntary flood buyback ever attempted in Australia — dwarfing the roughly 100 properties relocated in the land-swap that moved Grantham, Queensland, to higher ground after the 2011 floods (approx.; Queensland Reconstruction Authority, case study). Every transaction here requires a genuinely negotiated sale: an independent valuation, a household's free agreement, bridging arrangements while a family finds somewhere else to live, and — for those who want to relocate within the region rather than leave it — new, serviced, flood-free land that first has to be found, rezoned and connected to water, power and sewerage. NSW chose not to force anyone out through compulsory acquisition, which protects property rights and avoids the legal and political conflict a compulsory scheme would invite, but a consent-based program is inherently slower than one that can simply direct people to move.

The program also spans seven separate Northern Rivers council areas — Ballina, Byron, Clarence Valley, Kyogle, Lismore, Richmond Valley and Tweed — each with its own planning powers, plus five further Central West communities added after a second flood event the same year, meaning the Reconstruction Authority has had to coordinate with a dozen local governments at once (NSW Reconstruction Authority, 2026). It has also delivered real things: 546 temporary dwellings built across purpose-made villages at the height of the housing shortage, a $29.8 million modernisation of Lismore's CBD flood-pump network completed in 2026, and, as at 31 March 2026, 793 households who had accepted a buyback and settled it — a majority of the revised target, and 793 families who can now say the state has bought the flood-exposed home that nearly killed them (NSW Reconstruction Authority; NSW Audit Office, 20-May-2026).

The evidence

Set against that genuine complexity, the primary record — chiefly the NSW Audit Office's two performance audits of the flood recovery, in February 2024 and May 2026 — shows a program whose parts are moving at very different speeds. The 2024 audit, covering the emergency and temporary housing response, found "there was no plan in place to guide a temporary housing response" when the floods hit, despite temporary housing having already been used in the 2019–20 bushfire recovery. Against an estimated peak demand of around 1,642 households, only 546 temporary dwellings were ever built in the purpose-made villages, and of the first 75 households who exited temporary housing by mid-2023, only 30 moved into a long-term home — the rest left for reasons the audit could not always establish, including eviction (NSW Audit Office, 22-Feb-2024).

The May 2026 audit, examining the Resilient Homes and Resilient Lands Programs together, is starker. It found neither program had a business case or a cost-benefit analysis before it was rolled out, and that basic planning — detailed project plans, risk mitigations, milestones — was missing from the start, with the supporting Resilient Lands Strategy still significantly delayed years after it was first needed (NSW Audit Office, 20-May-2026). As at 31 March 2026, four years and one month after the floods, the figures were these:

$980m
Combined RHP + RLP budget
NSW Audit Office, 20-May-2026
793
Buybacks settled, of a revised 1,000
NSW Audit Office, 20-May-2026
54
Home raises/retrofits done, of a revised 600
NSW Audit Office, 20-May-2026
0
Land lots delivered under the RLP, of 4,382 promised
NSW Audit Office, 20-May-2026
0% 25% 50% 75% 100% Buybacks 79% (793/1,000) Raises & retrofits 9% (54/600) RLP land lots 0% (0/4,382)
Chart · share of revised delivery targets met, as at 31 March 2026 · Source: NSW Audit Office, The Resilient Homes and Resilient Lands Programs, 20 May 2026

That last line is the one that should concern anyone watching the program, because the Resilient Lands Program is the piece meant to give bought-back households somewhere nearby to go. Without it, a "buyback" for many families has not meant relocating within their own community — it has meant leaving it (NSW Audit Office, 20-May-2026).

The critique

The absence of a business case or cost-benefit analysis is not, on its own, proof of bad faith — disaster responses are often launched in an emergency, under real time pressure, without the luxury of a normal Treasury approval process. But the program is now approaching its fourth anniversary, and the government that has run nearly all of that time is Labor's, not the Coalition's that launched it in a hurry in late 2022. A rushed start can be forgiven. It is harder to excuse years of the same government failing to close the basic planning gaps the Audit Office says persisted into 2026, including a Resilient Lands Strategy that remained significantly delayed years after it was first flagged as necessary (NSW Audit Office, 20-May-2026).

The August 2025 decision to cut the buyback target from 1,345 to 1,000 households, and shift some of the difference into raise-and-retrofit grants, may well have been the right call — it followed community feedback, and some households always preferred to stay and rebuild rather than sell. But rescoping a headline target three years into a four-year program, without a clear public account of why, makes it hard for anyone outside the Reconstruction Authority to judge whether the program is ahead of or behind where it should be. A family deciding whether to wait for a buyback offer or take a lesser grant and rebuild now needs a program that tells them plainly where they sit and how long the wait actually is. The record suggests communication has lagged the scale of the decisions being made.

The raise-and-retrofit numbers are the sharpest illustration of a program moving at two speeds. Buybacks, at 793 of a revised 1,000, are the furthest along, because a buyback is a single transaction: an offer, an acceptance, a settlement. Raises and retrofits, at 54 of a revised 600, require something harder — engineering assessment, building approval, a contractor, and a household able to live elsewhere during the works — and the Audit Office's finding of no advance planning shows up directly in that gap. It also collides with a problem the government does not fully control: insurance. The Actuaries Institute found, in a report published in August 2024, that more than half of Northern Rivers households face home insurance premiums exceeding a full month's gross income, against a national affordability-stress rate of around 15% (Actuaries Institute, Home insurance affordability, Aug-2024). A household that spends years and its own co-contribution raising a house above flood level can still find the resulting premium unaffordable once the work is done.

Underneath all of it sits a slower, quieter number: people leaving. The Australian Bureau of Statistics recorded Lismore local government area's population at 45,938 at the August 2021 Census; its most recent estimated resident population, for June 2023, was 43,907 — a fall of 2,031 people in under two years, in an area that had not previously been shrinking (ABS, Census 2021; ABS Estimated Resident Population release, Jun-2023). Some of that fall is buybacks working as intended, moving households out of harm's way. Some of it, on the Reconstruction Authority's own figures, is families who stopped waiting.

Zero homes delivered under the Resilient Lands Program, four years on, is not a delay families can be told to be patient about. It is an answer they have been left to work out for themselves.

It took until March 2025 — three years after the floods — for recovery to become a dedicated Cabinet portfolio, when Lismore's own state MP, Janelle Saffin, was sworn in as Minister for Recovery, Small Business and the North Coast (NSW Government, ministerial appointment, Mar-2025). That a local member with direct knowledge of the Reconstruction Authority's workings now holds the recovery brief is a reasonable, defensible choice. That it took three years to make recovery a Cabinet-level responsibility in its own right is a fair measure of how long communication and accountability lagged the scale of what communities were living through.

The risk to the future

The risk to the future

A town that keeps flooding while it waits to be made safe

None of the underlying hazard has gone away. CSIRO modelling published in June 2026 found that a coordinated package of flood-mitigation works — detention basins and infrastructure upgrades across the Richmond River catchment — could cut peak flood levels in Lismore by up to roughly 2.1 metres in a repeat of the 2022 event, but that work is still at the feasibility stage, backed so far by a joint Commonwealth-state study worth $3 million rather than a funded construction program (CSIRO, Jun-2026; NSW Government, ministerial release, 2026). Until that mitigation, the Resilient Lands Strategy and the raise-and-retrofit backlog are actually built, Lismore remains a town where thousands of households still live below a flood line already reached twice, where insurance is becoming unaffordable for people trying to stay, and where every year of delay is a year in which the next east-coast low or ex-tropical cyclone can arrive before the recovery does. A program that eventually finishes on paper, in a river system that is still exposed, is not the same thing as a town that has actually been made safe.

Sources

  1. NSW Audit Office, The Resilient Homes and Resilient Lands Programs, performance audit report, 20 May 2026 — audit.nsw.gov.au
  2. NSW Audit Office, Flood housing response, performance audit report, 22 February 2024 — audit.nsw.gov.au
  3. NSW Flood Inquiry (M. O'Kane & M. Fuller), Report of the NSW Flood Inquiry, NSW Department of Premier and Cabinet, August 2022 — nsw.gov.au
  4. NSW Reconstruction Authority, About the Resilient Homes Program, program fact sheet, current as at 2026 — nsw.gov.au
  5. NSW Reconstruction Authority, Home Buyback Fact Sheet, April 2026 — nsw.gov.au
  6. NSW Government, Work underway to modernise Lismore CBD flood defence system, ministerial release, 2026 — nsw.gov.au
  7. NSW Government, Saffin made Minister for Recovery, Small Business and the North Coast, ministerial appointment, March 2025 — nsw.gov.au
  8. Australian Bureau of Statistics, Census of Population and Housing, Lismore LGA, 2021, and Estimated Resident Population release, June 2023 — abs.gov.au
  9. Actuaries Institute, Home Insurance Affordability Update, August 2024 (secondary source; national actuarial research body) — actuaries.asn.au
  10. CSIRO, Northern Rivers Resilience Initiative and Richmond River catchment flood-mitigation modelling, June 2026 (secondary source; Commonwealth science agency) — csiro.au